Complete the IEEE definition: a baseline is formally reviewed and agreed, thereafter serves as the basis for further development, and can be changed only through ___.

Complete the IEEE definition: a baseline is formally reviewed and agreed, thereafter serves as the basis for further development, and can be changed only through ___.

Answer

formal change control procedures

The third clause is the one candidates drop, and it is the clause that distinguishes a baseline from any other saved version.

Pressman 9e ch22 §22.1–22.4